Non-functional Requirements as User Stories

Friday, November 21st, 2008

A common challenge with writing user stories is how to handle a product’s non-functional requirements. These are requirements that are not about specific functionality (“As a user of a word processor, I want to insert a table into my document.”), but are rather about an attribute or characteristic of the system. Examples include reliability, availability, portability, scalability, usability, maintainability. As you can see from that list, non-functional requirements are often referred to as “-ilities”. Of course, not all non-functional requirements end in “-ility.” We also have security, performance, robustness and so on.

Thinking back into the dark ages, I can remember when I first read about “non-functional requirements.” The term threw me for a loop. “If it’s non-functional, why do I care about it?” I’m sure the author of that book clarified this for me a page later, but the term has always seemed an odd one to me. I prefer to think of non-functional requirements as “constraints” we put on the system. When a product owner says “this system must perform adequately with 100,000 concurrent users” the product owner is putting a constraint on the development team. The product owner is effectively saying, “Develop this software any way you’d like as long as you achieve 100,000 concurrent users.” Each constraint we put on a system narrows the design choices a bit; calling these “constraints” rather than “non-functional requirements” helps us remember this.

Fortunately constraints / non-functional requirements can be easily handled as user stories. Here are a couple of examples:

  • As a customer, I want to be able to run your product on all versions of Windows from Windows 95 on.
  • As the CTO, I want the system to use our existing orders database rather than create a new one sot that we don’t have one more database to maintain.
  • As a user, I want the site to be available 99.999% of the time I try to access it so that I don’t get frustrated and find another site to use.
  • As someone who speaks a Latin-based language, I might want to run your software someday.
  • As a user, I want the driving directions to be the best 90% of the time and reasonable 99% of the time.

As you can see from these I was quite easily able to stick with the “As a <type of user>, I want <some goal>, so that <some reason>” template that I prefer for most user stories. I do this for a couple of reasons but want to comment further on only one of them here. Consider the example of the CTO constraining the team to use the existing orders database. (This was the real situation; the team was considering a second orders database that would be sychronized at night. The CTO overheard this and said “no!”) If we wrote this requirement as simply “Must use existing orders database” it would be entirely possible that a few months down the road we wouldn’t remember why we should be constrained in that way. We’d ask the product owner if she cared if we used a secondary database, and she’d say she had no objections. And we’d make a mistake of using one. Embedding the person who wants something can be very useful.

But, you should be careful not to get obsessed with that template. It’s a thinking tool only. Trying to put a constraint into this template is a good exercise as it helps make sure you understand who wants what and why. If you end up with a confusingly worded statement, drop the template. If you can’t find a way to word the constraint, just write the constraint in whatever way feels natural

Visualizing a Large Product Backlog With a Treemap

Wednesday, July 2nd, 2008

In the early days we promoted agile project management only for small teams because that was where it originated. We had plenty of experience to say that agile worked well on seven- to ten-person teams. We were also quick to learn the techniques that allowed agile project management methodologies to scale up to around 20-40 people.

These days, though, there are many truly large projects being done with agile methodologies. In preparing for this posting I started counting on my fingers the number of 100+ person projects I’m aware of. I quickly ran out of fingers. I’ve been involved in a couple of 500+ person projects and am aware of three projects that each have over 1,000 people. We are truly at the point of doing large scale agile.

Unfortunately, the charts and tools we use for such large projects have not entirely caught up with us. For example, the time-tested Scrum burndown chart is absolutely wonderful but is really limited to showing only one thing: a single team’s rate of progress through their product backlog. This month I want to write about visualizing large product backlogs using a technique I’ve been advocating with my clients for three years but will be writing about here for the first time.

Suppose you have a very large product backlog–such as one with lots of themes (groups of related user stories) or being worked on by multiple agile teams. The best way to visualize this product backlog is with a treemap. Treemaps were invented in the 1990s by Dr. Ben Shneiderman as a way of visualizing hierarchical (that is, tree-structured) data.

The following is a simple treemap of a two-story house:

treemap of two floors of a house

In this treemap, each rectangle is sized to represent the relative area of the room. From it you can see that the master bedroom is about twice the size of either kid’s room and a little larger than the downstairs family room. The combined green area of the downstairs rooms is slightly larger than the area of blue upstairs rooms. From this very simple treemap you can get a feel of certain aspects of this house.

To visualize a product backlog with a treemap we need to conceptualize it as hierarchical data. We can do this a couple of different ways. For example,

Rental Car Theme

  • As a traveler, I can rent a car
  • As a traveler, I can get collision insurance on a car rental policy.
  • As a traveler, I can request a baby car seat be inside my car.

Airplane Theme

  • As a traveler, I can request an aisle seat.
  • As a frequent flyer, I can request an upgrade to first class.

Or we could create a product backlog as a tree with levels for

  • Team
    • Product Backlog Items Being Worked On By That Team

The following figure shows a product backlog as a treemap. There are five themes in the treemap. (Theme 4 is in the top left; Theme 1 is in the bottom right. You can click on it to enlarge it but be sure t come back.) Each theme is made up of a number of individual user stories. Story 4-28 (indicating the 28th story of theme 4) is in the top left. I’ve used this “theme-dash-story” notation for simplicity only for this example. I wouldn’t do that on a real project, of course.


a treemap

The size of each story in the preceding figure represents the number of story points that the story was assigned when estimated. Colors can be used on a treemap to represent an additional attribute of the data. On agile projects I’ve used colors to represent whether a user story has been developed or not. One color coding we used was:

  1. Done
  2. Started but not done
  3. Not started but not planned to have been started yet
  4. Not started but it should have been started by now
  5. Blocked

I’ve also used color to indicate which team would work on a user story / product backlog item or whether the item was ready for development or not. Treemaps are very flexible in this regard. Check out the link to the stock market as a treemap at the end to see a great example of using color.

A good treemap is interactive–you can mouse over, click on regions of it, and so on. For example, in the treemap above you’ll notice that some of the user stories of Theme 4 are so small you can’t read them. Clicking on a part of Theme 4 should zoom the treemap in so it displays only Theme 4, meaning more room is available and more detail can be shown as below:

Zoomed in on Theme 4

Sometimes zooming isn’t enough. A good treemap implementation will also display additional detail when mousing over part of it as shown in this example:

A treemap with an active popup

Treemaps are an excellent way of visualizing large product backlogs. To date, I’ve made use of various open source or relatively inexpensive general treemapping tools to create these on my projects or for my clients. Hopefully now some of the leading agile tool vendors begin to incorporate this type of visualization technique into their products. I would love to be able to visualize a large product backlog and interact with directly from within some of those tools. Until then, check out some of the links below for useful ways to create treemaps. The ones in this posting were created with IBM’s free Many Eyes tool.

Useful links:

  1. The stock market as a treemap
  2. IBM’s Free Many Eyes tool
  3. A good interactive example of a treemap
  4. Read news headlines as a treemap
  5. A simple JavaScript implementation you could add to your project homepage

Advantages of the “As a user, I want” user story template

Saturday, April 26th, 2008

In my user stories book and in all my training and conference sessions on user stories I advocate writing user stories in the form of “As a <type of user>, I want <some goal> so that <some reason>.” While I consider the so-that clause optional, I really like this template.

At a recent conference, someone asked me why. Because I get that question fairly often I want to give three reasons why here:

Reason 1
Something significant and I’m tempted to say magical happens when requirements are put in the first person. Obviously by saying “As a such-and-such, I want….” you can see how the person’s mind goes instantly to imagining he or she is a such-and-such. As for the magic, Paul McCartney was interviewed and asked about why the Beatles songs were so amazingly popular. One of his responses was that their songs were among the first to use a lot of pronouns. Think about it: She Loves You, I Wanna Hold Your Hand, I Saw Her Standing There, I Am The Walrus, Baby You Can Drive My Car, etc. His point was that these helped people more closely identify with the songs. I tried briefly to find a source for this interview tonight and the closest I found was this. The information in that reference fits my recollection of hearing McCartney says this during a radio interview in 1973 or 74 that I assume was recorded when the Beatles were together.

Reason Two
Having a structure to the stories actually helps the product owner prioritize. If the product backlog is a jumble of things like Fix exception handing, Let users make reservations, Users want to see photos, Show room size options, and so on, the product owner has to work harder to understand what the feature is, who benefits from it, and what the value of it is.

Reason Three
I’ve heard an argument that writing stories with this template actually suppresses the information content of the story because there is so much boilerplate in the text. If you find that true then correct it in how you present the story. I’ve seen backlogs in Word that present the boilerplate in grayed text with the unique parts in black. I’ve created product backlogs in Excel that use column headings to filter out the common text. Look and you’ll see what I mean:

sample user stories in Excel

Seriously take a look at the image above before continuing….I’ll wait……Please, really look at it before reading further…..

OK, here’s how I bet you read the spreadsheet. I bet that as you read most of the rows you added in the “As a…”, “I want….” and “so that….” text, possibly even by looking at the heading as you read across each row. I’ve experimented by asking people and this is what most people do. If that text is unnecessary, why do we mentally mouth the words to ourselves or even glance at the heading while reading the row? Perhaps it’s not so non-essential after all.

For now, and probably a long time to come, I’ll be sticking with the “As a <type of user>, I want <some goal> so that <some reason>” template for these and other reasons.

When Should We Estimate the Product Backlog

Sunday, March 16th, 2008

I was recently emailed a question asking whether the sprint planning meeting should start with time allocated for putting story point estimates on any user stories that have not yet been estimated.

No, I don’t think this is a good idea. Keep in mind that we put estimates on product backlog items (which I recommend be user stories) so that:

  • the product backlog can be prioritized. It is impossible to fully prioritize a set of items without knowing at least their relative cost.
  • we can make high-level forecasts about how much will be done by when
  • we can make tradeoff decisions between scope and schedule

We can achieve these goals with approximate, relative estimates such as given by story points. For example, if I decide to buy a new car this weekend it is sufficient for me to know that I can get a Toyota or Honda for around $30,000 and that a Ferrari goes for closer to $800,000. I do not need to know a more precise cost of the Honda ($31,850) before knowing it should be on my short list of cars to evaluate while the Ferrari should not.

Sprint planning meetings typically go into deeper detail than is appropriate for product backlog item estimating (whether in story points or ideal days). Since we become accustomed during sprint planning to breaking user stories into tasks and considering those tasks in more detail, there is a chance this will carry over into any story point estimating done during the same meeting.

So, when should story point estimating happen? I’ll describe the ideal case, which you can easily adjust for the real-world intrusions on your project. Projects typically start in either of two ways:

  1. A reasonably fully stocked product backlog is written before the first sprint begins and all items are estimated before the first sprint planning meeting. [If you do this, be careful not to write all user stories with too much detail. Each product backlog item you write represents an investment. User stories should therefore be elaborated just-in-time and in just-enough detail that they can be turned into functionality in one sprint.]
  2. We know we’ve got to do the project so we dive in. During the first sprint or two, all the user stories are written and estimated just like above.

On an ongoing basis, once per sprint I recommend that the ScrumMaster tell the team something like, “Hey, we’ve had five new user stories come in this sprint and we need to estimate them. Everyone plan on hanging around for a bit after tomorrow’s daily scrum meeting and we’ll play Planning Poker to estimate the new items.” Doing it right after the daily scrum helps cut down on the number of interruptions in total. I usually aim for having that meeting about two days before the end of the sprint. That way the product owner will have estimates on them so she can prioritize prior to the start of the sprint.