Distributed Teams: Build Trust through Early Progress

Monday, February 22nd, 2010

Critical to creating a coherent team is building trust among team members. This is much more difficult on a distributed team. Unable to rely on repeated, frequent face-to-face communication, distributed teams need to take other measures to build trust. Traveling ambassadors, starting meetings with casual conversations, occasional in-person meetings of the full team, working agreements, and similar activities all help. What also helps is early pressure for the team to produce working software by the end of each sprint, even the earliest ones.

Unfortunately, many projects schedule too much time for teambuilding exercises and discussions too early in the project. This is a common and dangerous mistake, as shown by research from Professor Lynda Gratton and her coauthors, as published in the MIT Sloan Management Review.

Guiding these diverse teams to success requires some counterintuitive management practices. In particular, team leaders should focus on tasks at the early stages, rather than on interpersonal relationships, and then switch to relationship building when the time is right. (Gratton, Voigt, and Erickson. “Bridging faultlines in diverse teams.” MIT Sloan Management Review, Summer 2007, 22–29.)

Though this research suggests that the early focus should be on tasks, I do not mean to suggest that product owners or ScrumMasters should be assigning tasks to developers. Rather, I mean that these leaders should emphasize the need for the team to make demonstrable progress even in the early sprints. The problem with an early emphasis on relationship building is that it encourages less-than-ideal subgroups to form. Any large group will inevitably split into subgroups. If these subgroups are allowed to form too early they will form around surface-level attributes—Americans, Swedes, C++ programmers, Java programmers, female database engineers, male programmers, and so on. As Gratton and her coauthors write, “Simply put, in a team’s early going, the more people interact with one another, the more likely they are to make snap judgments and to emphasize their differences” (26).

What we’d like to do is defer relationship building until team members have learned more significant things about each other, such as specific skills, competencies, approaches to work, and so on. This is done through early emphasis on progress rather than relationship building. The subgroups that form at that time will be based on the mutual need to work together to develop the product. To develop a particular user story from the product backlog, you and I need to work together. In doing so we learn each other’s skills and specific competencies. I come to know you not just as a Java programmer but as a Java programmer with a real passion and strength for automated unit testing. You find that I am not just a DBA, but one who is strong at optimizing SQL statements.

Teams with subgroups formed around compatible skills, attitudes, approaches to work, and so on are less likely to lead to a later breakdown in trust than subgroups formed on superficial attributes (such as American, Swede, programmer, tester, and so on). Think back to one or more troubled teams you were a member of. Odds are that conflict on those teams was of an us-versus-them nature based on superficial attributes: this office versus that office, programmer versus DBA, Linux fanatics versus Windows fanatics. When teams feel an immediate need to make progress, those types of subgroups do not have time to form.

After a team has worked together for a few sprints, shift the emphasis toward relationship building by incorporating more social activities and shared downtime into the sprints. A team needs to have a sufficient amount of shared experience before social activities and relationship building can be useful. But when that has been achieved, “instilling confidence in the team and creating opportunities to socialize at that point helps the development of new abilities and allows the team to grow” (29).

I want to be clear that I am not saying that no time for socialization should be included at the start of a project. Seeding visits and whole-team, in-person get-togethers at the start of a project for its initial release planning can be very useful. Three points are key here:

  • First, the project should start with intensity and a focus on early demonstrations of progress.
  • Second, the entire “budget” for socialization should not be spent in the first couple of sprints.
  • Third, early social activities should tie into the work of the project, such as bringing a team together for release planning.

Build Trust Between Teams with Ambassadors

Monday, December 28th, 2009

On a distributed Scrum project, individual team members need to meet each other face to face. If the whole team cannot get together, one or two members from each team, at least, should spend time visiting team members in other cities. Think of them as ambassadors. I’ve found that the personal relationships established by ambassadors can be extremely valuable even long after the ambassador returns to native soil.

On one project I coached, for example, I had developers in Denver and Toronto. Teams in the two cities had been thrust together on a common project because of an acquisition, which initially had led to an unfriendly relationship between the two teams. Frank, a programmer in Denver, volunteered for a couple of two-week visits to Toronto. I knew the Toronto developers very well, having already worked with them for two years. I wanted to make sure we got the most benefit from Frank’s trips, so I talked with him about his hobbies and interests outside of work. When I discovered he was a rock climber, I contacted Marcel in Toronto, who was an obsessive climber. I asked Marcel to do me the favor of spending a little time with Frank, possibly setting him up with a guest pass to his indoor rock-climbing gym. Marcel very willingly did so, and the two of them became good friends and discovered they had other interests in common as well.

The budding friendship between Marcel and Frank served the project well right from the start. But it really paid dividends a few months later when a potential conflict started to emerge between departments on the periphery of our two-city project. The IT staff in Denver had named a server “Pandora” that would be used by the Toronto team. The Toronto team was furious over this and assumed the name had been intended as an insult because of the mythological story of Pandora’s box containing all the evils of mankind. I was in Toronto when the trouble started, so I asked Marcel to get Frank on the phone and to ask him if he would discreetly find out if the name had been intended as an insult. Two hours later Frank informed us that the employee who selected the name pulled it from a previously generated list of server names and had no idea who Pandora was. Because of the trust built between Marcel and Frank, we were able to quickly defuse the situation.

I write a great deal more about working with distributed teams in Chapter 18, “Distributed Teams,” in Succeeding with Agile.

Using a Task Board with One Remote Team Member

Sunday, May 31st, 2009

I want to address a question I was emailed yesterday but that I receive frequently. What should we do in the case when the team really likes having a physical task board, but when one team member is remote?

My first answer is always: Try to get the one person to move to where the rest of the team is. I don’t expect to see any moving trucks roll out when I ask this, but I have to ask. I figured if I keep asking, some team somewhere will eventually have the person move. Having one remote is a cost that must be borne by the full team. For the right person, it’s easily worth it. But sometimes, the person who is remote has not special skills, knowledge or experience to justify the added hassle.

So, assuming that we’ve tried the “move here” solution and it didn’t work, what can a team do that likes the physical task board but that has one remote member?

My recommendation is to continue to use the physical task board–it is simply too beneficial to the collocated team members to give it up in favor of a product backlog tool, especially if team members are already used to it and like it. How the team conveys information on the task board to the remote team member depends on what that person does.

Sometimes the remote person works remotely because they have a very specialized skill that couldn’t be filled in the office where the rest of the team is. This would be the case, for example, if our remote person is an expert in Windows internals and is writing boot-time code in C++. It would also be the case if our remote person has twenty years of experience in the domain and with some of our really old code. In these cases, the remote person usually (not always) works for a day or two relatively alone. The remote person in this case could identify during the daily Scrum what he or she will work on and not need further interaction with the task board until selecting the next task. Here, the remote person doesn’t really interact with the task board at all and interacts only with the team. Not ideal as I’d like the person to see the tasks, but this can work in some situations.

What is more common is for the ScrumMaster to take on the responsibility of updating an electronic version that mirrors the physical task board. A shared spreadsheet is normally sufficient for this, but some teams opt for a more specialized tool, which is fine. Many tools offer 5-10 user free licenses and since the tool is only needed by the ScrumMaster and one remote employees, the free license is adequate.

Normally the ScrumMaster updates the electronic task board once a day, usually right after the daily scrum meeting. Of course, reading the physical task board and updating the electronic one can be quite time-consuming because the ScrumMaster has to look at each task in both places to see if that item needs to be updated.

One good way of minimizing the time the ScrumMaster spends doing this is to mark the cards on the physical task board. The mark indicates “I’ve updated this task. Please update it in the online task board.” I like to use Post-It flags for this. As team members do their daily scrum, they stick one of these flags (of any color) on the card. If the estimate changes, if the task is done, if a new task is added, those cards are tagged with a flag. When the meeting is over, the ScrumMaster can very easily see which items need to be updated. The ScrumMaster removes the flags once the online task board is updated. This approach also works in situations where the ScrumMaster updates the board more than once a day. Any time someone changes the board, flag the task.

Other teams do something similar using color-coded dots. Anything touched on Monday is blue, Tuesday is red, and so on. Two problems occur though: First, the dot packs usually come with four colors to a pack so you have to buy a fifth color. Second, it’s a hassle to make sure we have the right color on hand.